What to do if your Planning Permit Expires.
By Phillip Leaman
29 July 2013
Planning Permits have an expiry date by which the construction of the development must commence and finish.
Usually, construction will need to:
- commence 2 years after the permit is issued;
- be completed 4 years after the permit is issued.
What if an extension is required?
- Generally, the applicant will have until the expiry of the permit date and up to 6 months later (since 22 July 2013) to apply to the Council to request an extension. However, you need to review your permit conditions to determine what procedure applies to your permit.
- The application to the Council can be a straight forward process and particularly if it is the first extension, the Council is likely to grant the application.
What if you miss the deadline to extend?
- If the Council’s right to extend the permit under the permit conditions has lapsed then since 22 July 2013 you can no longer apply to VCAT for a review of the Council’s decision and ask the Tribunal to exercise its discretion (pursuant to Section 62 of Schedule 1 of the Victorian Civil and Administrative Tribunal Act 1998) to disregard the failure of the applicant to comply with Section 69(1) of the Planning and Environment Act 1987. The only time you can seek a review is if you made an application for an extension of time with the responsible authority prior to the expiry of 6 months after the permit expiry date.
- If an application is made to the Tribunal (after your application has been refused by the responsible authority, the Tribunal must be convinced that it is in the interests of nature justice to do so as well as a consideration on whether the relevant planning scheme has changed.
- The Tribunal must deal with the principles of law outlined in Kanto v Shire of Murrindindi (and various other authorities).
The importance of getting it right
- It is important that you consult a solicitor with experience in planning matters if an application for an extension of time (or any other planning permit amendment) is sought as the effect of not properly preparing could mean that the applicant is denied the extension and forced to make a new application.
- If the Tribunal is of the view that the planning scheme has changed since the permit issue date, the Tribunal may reassess the entire permit application as part of its consideration of whether to grant the permit. This may mean the Tribunal insists on substantial changes to your plans or permit conditions or that a fresh application is made.
- Our firm recently had a matter where the Council consented to the application for an extension but the Tribunal ordered a Practice Day Hearing to consider the issues prior to agreeing to the extension.
For expert planning advice please contact Phillip Leaman or a member of our Property Law team.
Related Articles
View AllOccupancy permits – the ticking clock in defective building work
Where multiple occupancy permits are issued in relation to a building permit, which permit is the operative permit for...
The 1, 2, 3 of Property Law Reminders for NY2023
In so reflecting, reflecting on one’s property matters (current or proposed for the future) is also a worthwhile...
By Nafsika Starvaggi
15 February 2023
Section 9AC of the Sale of Land Act – What does ‘materially affect’ mean?
Throughout the registration period, a Plan of Subdivision may undergo many amendments from the proposed Plan which was...
Paving the way to land ownership: How to claim adverse possession without fences
There are three main requirements for an adverse possession claim which are as follows: Actual Possession – You will...
By Phillip Leaman
21 May 2019
Could you Be Contaminated?
Whether you are the purchaser of land, the seller, a landlord, a tenant, a developer or a lender, there are obligations...
By Michael Fetter
7 May 2019
Loss of Properties under North East Link Imminent
The current North East Link project intends to have the following effect on businesses and landowners according to the...
By Phillip Leaman
11 April 2019
Cladding Rectification Agreements: what you need to know about getting a loan to replace flammable cladding
The new legislation, which came into effect of 30 October 2018, will enable local councils to enter into a cladding...
By Sophie Chessells
28 November 2018
TLFC – Award Finalist for Law Firm of the Year (Medium Category)
Tisher Liner FC are proud to be nominated as an award finalist in the 14th annual Victorian Legal Awards Medium Law...
Case Law Update: Developers Watch Out – No Cost Land Grabs by Councils Can be Legal
In an early Christmas present from the Tribunal on 22 December 2017, the Tribunal in Tarneit Projects Pty Ltd v Wyndham...
By Phillip Leaman
12 February 2018
Roads – What are they and how do you get rid of them
What are Roads Roads can include streets, rights of way, passages, bridges, footpaths, kerbing and public highways...
By Phillip Leaman
20 November 2017
Planning Minister puts a limit on CBD apartment tower heights for now
The Controls have been introduced pending the larger review called the Central City Built Form Review which is being...
By Phillip Leaman
16 September 2015
New Victorian Planning Zones to change the development landscape.
Residential Zones – So what has changed The existing Residential 1 Zone, Residential 2 Zone and Residential 3 Zone...
By Phillip Leaman
12 August 2013